## Criterion B: Record of tasks
| Task Number | Planned Action | Planned outcome | Time estimated | Target Completion Date | Criterion |
|:---|:---|:---|:---|:---|:---|
| 1 | Talk about project with Orsen | Project description is defined | 1 Day | September 5 | A |
| 2 | Confirm project plan with Pak Hidayat | Project description is confirmed | 8 Days | September 11 | A |
| 3 | Choose which tools will be used to create the project | Criterion A Rationale will be complete | 1 Day | September 18 | A |
| 4 | Create success criteria | Criterion A will be complete | 1 Day | September 18 | A |
| 5 | Make schedule of product development | Criterion B will be complete | 2 Days | September 19 | B |
| 6 | Start research into ReactJS and learn how to use it | Be familiar with the usage of ReactJS | 3 Day | September 23 | C |
| 7 | Create structs and functions and database interface for the backend | Project base will be developed | 6 Days | September 29 | C |
| 8 | Write tests making sure the database interface functions | Project base will be completed | 2 Days | October 1 | C |
| 9 | X | X | X | X | X |